We have a requirement to close the case when user started it and haven't finished for 30 days (stays in the first stage). The option to create a temporary case is checked on the case settings. I created an SLA with the Goal of 30 business days and conditionally ((when pyID is present) run an activity pxForceCaseClose. I applied it on the first stage flow, it didn't work. I applied on the stage itself, it didn't work either (no records created in System-Queue-ServiceLevel class). Can somebody advise what I need to do to make it work?
Any help is appreciated!
Thanks,
Larisa