Stop running campaigns on Public holiday.
Hi All,
I have a requirement to stop running a campaign on Public Holidays . Is there any OOTB way of acheiving this?
I tried assigning a Business Calendar with required dates under Closed Days to the Work queue ScheduledPrograms of Pega-MKT engine, but it does'nt seem to take into effect.
Also tried, in the OOTB Organization PegaNBAM rule to add a calendar preference. still it continues to run.
For Campaigns,Work Queue Preferences does not work in Pega Marketing?
Last option, is to modify the ProcessProgramRun activity to include isBusinessDay check which I want to avoid.