Production level and draft mode
Hello!
We change production level from 2 to 5 in system instance and restart the server (including removing extract marker).
However, flows with enabled draft mode are still being executed correctly.
Is this normal behavior? PDN says that draft flows are not allowed on production level 5 systems.
Thanks,
Yuriy Berdnikov
**Moderation Team has archived post**