Question
Nordea
SE
Last activity: 19 Jul 2019 4:27 EDT
Pega Upgrade Time
Hi,
We recently upgraded Pega from 7.3.1 to 8.2.1 in two of our lower environments SIT & BAT. The upgrade was done via in-place manner. We observed that SIT took 130 minutes to upgrade whereas BAT took 330 minutes to do the same. Both the environments have same Rule Base & approx same Data. I was just curios what are the other factors we should check which may impact upgrade time because the downtime would play crucial role during production upgrade and we have to plan it accordingly.