Change Assignment Urgency Value within activity
I need to decrease the Assignment urgency value from the Escalation activity, How to achieve the same?
This content is closed to future replies and is no longer being maintained or updated.
Links may no longer function. If you have a similar request, please write a new post.
I need to decrease the Assignment urgency value from the Escalation activity, How to achieve the same?
Hi Sudip,
Can you try setting/adjusting appropriate/negative value to pyUrgencyWorkAdjust .
Regards,
Ujjwal
You can use of property Assign-.pyUrgencyAssignAdjust to adjust the urgency values .
For more information please go through below article
https://community.pega.com/sites/default/files/help_v72/procomhelpmain.htm
You can use of property Assign-.pyUrgencyAssignAdjust to adjust the urgency values .
For more information please go through below article
https://community.pega.com/sites/default/files/help_v72/procomhelpmain.htm
Thanks,
Arun
Question Solved
Discussion
Question Solved
Question
Question
Support Doc
Question
Question
Question
Question
Pega Collaboration Center has detected you are using a browser which may prevent you from experiencing the site as intended. To improve your experience, please update your browser.