Module Quiz Help - Designing an approval process
Hi, I need help on below quiz question:
Fill in the missing words in the following scenario.
A senior engineer approves code changes on a specific part of an application, so those approvals route to their___ . Other code changes can be approved by anyone on the engineering team, so approvals will route to the team's___ .
I am able to fill out the 2nd blank, which is "work queue", but I cannot get right on the 1st one. I have tried "senior engineer worklist", "senior engineer work queue", "senior engineer team's work queue" and many others.
Can someone helps me here? Thanks.
Accepted Solution
Updated: 2 May 2022 2:01 EDT


Tech Mahindra
IN
@ArielL44 just fill it with worklist


Perficient Inc
US
I had the same issue. "worklist"? Where did that come from? It does answer the question....


tp
IN
I was reading it and tried to solve that


Walmart
US
A senior engineer approves code changes on a specific part of an application, so those approvals route to their WORKLIST. Other code changes can be approved by anyone on the engineering team, so approvals will route to the team's WORK QUEUE.


IBM
IN
first blank -worklist
second blank -work queue


Virtusa Ltd
LK
@ArielL44 first blank - work queue
2nd blank - work queue
A senior engineer approves code changes on a specific part of an application, so those approvals route to their work queue . Other code changes can be approved by anyone on the engineering team, so approvals will route to the team's work queue.


Walmart
US