Time spent at each stage report
Is there any OOTB way of reporting age of work object at each stage (assignment). Customer need is to report time spent on each stage for that case?. Does History table provide full information and if yes, what fields does provide the information. Thanks.
Using Pega 6.1 Sp2.
***Updated by moderator: Marissa to update categories***
Hi Surendra,
May be you can use pxTaskElapsedTime from the history table to calculate the time that a task was worked on; the sum of pxElapsedAssignmentTime's.