Question


Cognizant
AU
Last activity: 7 Apr 2017 9:24 EDT
Multiple Processes
Hi,
I am trying to run 2 processes at the same time, it is throwing an error for this.
I want to run 2 processes(i.e., 2 different solutions) at the same time, how can I achieve this.
Regards,
Lekha
***Updated by moderator: Lochan to add Categories***
-
Like (0)
-
Share this page Facebook Twitter LinkedIn Email Copying... Copied!


Pegasystems Inc.
IN
Hi,
Is it that you wanted to start two processes at the same time.
If yes, check if this option helps ?


Pegasystems Inc.
IN
Hi Srilekha,
If I understand your requirement properly, you can create 2 multistep processes and enable step upon stage entry for both the processes . Hope this helps.
Regards
Saran


Pegasystems Inc.
IN
What exactly do you mean by process here ? Is this related to Case management ? Also could you share screenshots of the errors that you are getting.


Pegasystems Inc.
IN
Hi,
You can also use split- join shape in the flow. This is one approach to run both the processes simultaneously.


Cognizant
AU
my query is for Pega Robotics Automation 8.0


Pegasystems Inc.
US
Are you attempting to do this using RDA? If so, you can only run one process at a time. Robotic Activities are queued and will run sequentially. You will only be able to run a single solution - it will have to service both of your requests.


Cognizant
AU
Thanku :)