Agent Schedule - Is being created for the highest version even though the rule availability is set to "No"
I have an agent rule (Rule-Agent-Queue) in 2 versions of a Ruleset (ABC).
Eg :
ABC : 01-01-01
ABC : 01-01-02
As the 02 version is still in development, i put the rule availability of it to "No". So that the version 01 is in effect and its activities are executed.
Then deleted the existing Agent Schedules (Data-Agent-Queue). However found that the new Agent schedules are being created still for the 02 version instead of the 01 version.