Hi
I have an activity to start a new flow.
So, I add step Flow-New Nameofflow. Then it can add a new task to the case. But, we need to click on "Go" to continue the flow.
Is there any method we can use to continue the flow directly after step Flow-New?
Thank you
***Edited by Moderator Marije to add Capability tags***
@Intandhp you need to open the assignment then. Whatever open assignment action set does by taking assignment handle as parameter you need to do using activity. Not sure the below approach will work directly(creating a flow and opening an assignment without any user intervention), try using Work-Perform activity to open the assignment by passing assignment handle.